Phase Graph

Living Room

PDF-style phase graph with linear flow, overlapping phase view, common scenarios, and phase percentage breakdowns.

Back to Project

Total Modeled Duration

98 days

Order Release

Move-In

Planning & Design

Programming, design development, client approvals, FDP.

36%

35 days

Procurement

Proposal, BOM, RTO, approvals, order entry.

5%

5 days

Production

Manufacturer production, transit, receiving, inspection.

41%

40 days

Installation

Delivery, install, punch, closeout, move-in.

18%

18 days