Cassidy & Associates

Cassidy Base Schedule

Location: Washington, DCAward: 2026-04-08Status: activeSchedule: nextBaselines: 0

Health

red

Move-In

2026-05-21

Order Release

2025-12-12

Variance

-125 days

Project Ownership

Executive Summary

Live AI

Forecast shows an accelerated move-in date compared to baseline. The project is currently marked red based on schedule health, compression, and milestone risk.

Recommendation: Validate order release feasibility before committing to the current forecast.

Critical Dependency

Order Release Required By

2025-12-12

To hit move-in on 2026-05-21, this release date must be protected.

Health

red

Baseline Move-In

2026-09-23

Locked reference

Forecast Move-In

2026-05-21

Current calculated plan

AI Summary
Click a line for detail
Generating…

Generating summary...

Critical Schedule Risk

design_days is below minimum (1 < 3)

Blackout Impact

Blackout dates are contributing 3 days to the schedule.

Phase Flow

Project phasing map

High-level view of how this project flows from proposal through planning, procurement, production, installation, and move-in.

Proposal / RFP

RFP issued, response, review, award.

Key Date: 2026-04-08

Planning & Design

Programming, design development, client approval.

Key Date: 2026-04-08

Procurement

Proposal, approvals, RTO, order entry.

Key Date: 2025-12-12

Production

Manufacturer lead time, shipment, receiving.

Key Date: 2025-12-12

Workstation

Steelcase40 days

Private Offices

Kimball60 days

Installation

Delivery, install, punch, closeout.

Key Date: 2026-05-21

floor 1

first floor • Install 40 days • Punch 2 days

Construction

External phase. Track start/end only for now.

Mock-Up

Optional branch for mock-up review and approval.