Phase Graph
Cassidy Base Schedule
PDF-style phase graph with linear flow, overlapping phase view, common scenarios, and phase percentage breakdowns.
Total Modeled Duration
148 days
Order Release
2025-12-12
Move-In
2026-05-21
Proposal / RFP
RFP issued, RFI, interview, award.
7%
10 days
↓
Planning & Design
Programming, design development, client approvals, FDP.
1%
1 days
↓
Procurement
Proposal, BOM, RTO, approvals, order entry.
3%
5 days
↓
Production
Manufacturer production, transit, receiving, inspection.
41%
60 days
↓
Installation
Delivery, install, punch, closeout, move-in.
28%
42 days
↓
Construction
Field dimensions, core drills, rough-in, site readiness.
14%
20 days
↓
Mock-Up
Mock-up fabrication, review, approval.
7%
10 days