Phase Graph

Cassidy Base Schedule

PDF-style phase graph with linear flow, overlapping phase view, common scenarios, and phase percentage breakdowns.

Back to Project

Total Modeled Duration

148 days

Order Release

2025-12-12

Move-In

2026-05-21

Proposal / RFP

RFP issued, RFI, interview, award.

7%

10 days

Planning & Design

Programming, design development, client approvals, FDP.

1%

1 days

Procurement

Proposal, BOM, RTO, approvals, order entry.

3%

5 days

Production

Manufacturer production, transit, receiving, inspection.

41%

60 days

Installation

Delivery, install, punch, closeout, move-in.

28%

42 days

Construction

Field dimensions, core drills, rough-in, site readiness.

14%

20 days

Mock-Up

Mock-up fabrication, review, approval.

7%

10 days